Mariposa Ave Safe Routes to School Phase 4

Project Description

The Mariposa Avenue Safe Routes to School Phase 4 Project is the final phase of 1.2 mile Safe Route to School project providing complete streets connections between Greenback Lane and Madison Avenue encompassing Skycrest Elementary, San Juan High School and San Juan Park. 

This Project will complete the bicycle and pedestrian network between Northeast Circle and Madison Avenue including:

  • 1600 linear feet of sidewalk, curb and gutter
  • 3200 linear feet of bike lanes
  • upgrades to the Madison/Mariposa traffic signal
  • street lighting
  • 5 new accessible curb ramps

Project Status:

The project is in the final design phase and is nearing completion.  Construction is anticipated to commence in April 2021.

Community Engagement: 

Thank you to those who attended the informational Open House on Thursday, December 6, 2018.

View the Mariposa Ave Safe Routes to School Open House Invitations:

 ENGLISH (PDF), SPANISH (PDF), and RUSSIAN (PDF)

If you were unable to attend the informational Open House and would like additional information about the projects or if you would like to provide feedback, please contact the General Services Department at 916-727-4770.